Sem Driveway Project Update – June 8, 2015

Since our last post on the progress of the PRC Seminary driveway/parking lot project, we can bring you up-to-date on a few things.

Last week the new light pole bases that will line the new drive and the backside of the parking lot were set and poured by Fliers Trenching.

DSCN4600

And then the final coat of asphalt was added last Monday by A-1 Asphalt – prepping first with the big brush.

Brushing off the base coat for the final coat of paving.

Brushing off the base coat for the final coat of paving.

Now the application of the asphalt:

DSCN4610
DSCN4612

And this is how it all looked when the job was done:

DSCN4614
DSCN4617
DSCN4627

And this now is the view from the new street entrance (Scenic River), just around the corner from the old drive:

DSCN4618
DSCN4623

Today Schepers finished the underground sprinkling, so now Kregels Landscaping can come in to seed the grass and do the landscape around the new sign when that is completed.

Published in: on June 8, 2015 at 4:48 PM  Leave a Comment  

The URI to TrackBack this entry is: https://cjts3rs.wordpress.com/2015/06/08/sem-driveway-project-update-june-8-2015/trackback/

RSS feed for comments on this post.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

%d bloggers like this: